Metro construction work completed till Radisson

31 October 23

Now track laying work will start soon.

Indore •

Metro work has gained momentum. After the trial run, the construction work of three major parts of the metro has also been completed. Now soon it will be handed over to another agency for laying the track. She will work on laying tracks on it. The trial run of the metro was done on 30 September. In this trial run, the Chief Minister also traveled in the metro along with some selected passengers. After this, the construction work of three big stretches from MR-10 to Hiranagar and Bapat intersection to Meghdoot and then about two and a half kilometers from here to Radisson has been completed. Now track will be laid on this part soon and other works will be started. Along with this, the work of laying pillars between Radisson intersection and Robot intersection has also almost been completed. Here also the work of laying the slab will start soon.

Target of passenger operation in 7 months

At the time of the trial run, officials associated with the metro had said that a target of seven months has been set for starting the metro. During this period, there was talk of starting passenger operation between Gandhi Nagar and Radisson. Looking at the way the work is going on, it seems that the route will soon be opened for passengers.

Metro at a glance

  • There will be a 31 kilometer route in the first phase.
  • There will be 28 metro stations in Indore. These will have 7 underground and 21 elevated stations.
  • The metro will run at a speed of 80 kilometers per hour, the length of a coach will be 22 meters.
  • There will be security system in every coach with the help of AI. Through AI, arrests can be made through CCTV cameras in Kot.
  • Along with this the driver will be equipped. Along with this if there is any kind of disturbance in the track, the train will stop automatically.

Easy way to operate long distance trains from Mhow, passengers will get benefit, Railway officers took trial of third pitline, work completed.

The third pit line has been ready at Mhow railway station of Ratlam division. Train operation trial was conducted on the pit line in the presence of railway officers. It was completely successful. Now the operation of long distance trains has also become easier. Passengers will benefit from this. Not only this, the pressure of trains will also reduce at Indore station.

Actually, the work of third pit line for maintenance of trains was going on for a long time at Mhow railway station. This pit line was completed recently. Since earlier meter gauge trains were operating in Mhow. Broad gauge line is also being laid here. The work of broad gauge station has also been completed. Due to this, a third pit line has been prepared in the yard. Yesterday, rake run of Malwa Express was done on this third pit line. Railway officials were also present during this period. After the successful trial, it has now become easier for long distance trains to operate from here. Let us tell you that earlier the maintenance of Malwa Express was done in Indore only, but later it was extended to Mhow. Similarly, now long distance trains like Avantika and others can be operated from Mhow. This will also reduce the pressure on Indore station and passengers will also get long distance train facilities from Mhow.

Will start ready in two years

Experts say that maintenance in trains third pitline now complete for it is ready. The third pit line, prepared in about two years, was tested. Now maintenance of passenger trains will be started. At present, maintenance of Malwa Express, Yesvantpur-Mhow-Nagpur, Mhow-Bhopal Intercity, Kamakhya Express and DEMU trains from Mhow station is being done from two pit lines.

At present only DEMU train will be maintained

Railway officials said that the third pit line has not been electrified. Due to which only the DEMU trains running on diesel locos will be maintained from here. At the same time, maintenance will be done on both the old pit lines as the number of trains increases.

The work will be completed within a week

According to the information, the work of laying track on the third pit line has been completed, but the connectivity of pipes and electricity has not been completed yet. These works will be completed within a week. After this train maintenance will be started.

Source-Dainik Bhaskar

Latest News
Metro line will be laid over the railway line.. steel girder reached Hiranandani Group Ventures into Property Development Management Rs 4 crores. Sales of more expensive luxury homes doubled in 9 months Steps towards metropolitan: Indore: Industries doubled in 12 years, per capita income increased five times in 16 years Multimodal transport hub will connect two ends of the city with metro station. Metro speed: 33 kilometer ring will be completed in 2026, metro will reach Ujjain in Sihastha of 2028 Lakhs of saplings will be planted, that is why it has been named Green Corridor.65 km green Indore will build corridor development Authority Rents in 13 major cities grow 22.4% in July-Sept Metro took the launcher for construction of turn track on Ring Road Chalet Plans to Invest ₹300 crore in New Luxury Hotel at Delhi Airport Mumbai’s Luxe Housing Market on a Song The bridge is waiting for the road… only ten percent work left… RIL Plans to Invest *20k cr More in Bengal in Next 3 Years: Ambani Everest Food Promoter Buys 73-cr Luxury Flat in Mumbai Indians Dethrone British in Dubai Real Estate Market The scope of green building is increasing in India, Bengaluru is at the forefront. India Top Scorer in Asia-Pacific For Consumer Goods Biggies Realtors Put a Lock on Festive Offers Amid High Demand Brookfield Properties Refinances 2.1ker Debt 9 pillars of Footi Kothi Bridge constructed, pier caps being installed Godrej Properties on Track to Exceed Full-year Guidance on Robust Demand Metro construction work completed till Radisson Institutional investment in realty increased by 82% in 3 months till September Sales of luxury homes doubled in Delhi-NCR Robust Demand in Major Cities Keeps Indian Office Market Busy Oberoi Realty Sells its Entire Stake in Pune Township Project JV India ‘Priority Market’, M&S Accelerates Store Expansion Understand the legal implications before taking a loan against property Retail space lease increased by 46 percent in just 9 months Office Space Offtake all Set to Boom One and a half km long three layer flyover will rest on 8 pillar and 3 RE walls. Property Market Scales New Heights in Mumbai Bhoomipujan of bridge and inauguration of swimming pool at Lavkush intersection on 30th September Survey of private properties started for Metro underground track on MG Road, seven stations to be built here 84% OF 2,181 ACRES ALLOCATED FOR HSG IN OVER A YEAR Experion Buys 3 NCR Plots in Rs1.1Kcr Deal 20 more colonies will be legal, a guest house will be built for relatives of patients in MYH, and the road will be wide for the Mhow Naka bridge 85% increase in PE investment Indore’s master plan will be made only for 2041 Prestige Pockets SoBo Land for over Rs704 cr ‘Global Capability Centres Boost Indian Office Leasing’ Bhanwarkuan, Khajrana, Footi Kothi and Lavkush intersection on Monday Gift City to Deepen India’s Integration with Global Finance Carbon’s social cost is upto three times higher than estimated Yearning playgrounds ‘Capital of Sports’ REAL ESTATE FIRMS STUCK IN INSOLVENCY ‘India’s Seeing a Consumption Boom’ Intel to Sell Bengaluru Office and Lease it Back Transport complex in new loha mandi INDORE METRO TRIAL RUN UPDATE Country’s second largest ring road will be built in Indore MALLS WORRIED OVER THINNING FOOTBALLS AT MULTIPLEXES KAPPIRI, HABSHI AND AFRICAN SLAVE GODS THREE MODELS OF STARTUP COMPLEX ROCHE INDIA ARM PICKS UP 2L SQFT ON LEASE Road from Ringnodiya to Dakachya will be built by recycling method, Indore, Ujjain-Dewas will get link Retailers, eateries expand play to cash in on rising demand Cognizant Renews Two Lease Deals For Pune Office Space Preparation started for the Three Bridges to be built on the Bypass. Ward- wise Masterplan to be released: Three model roads planned between Navlakha and Teen Imli Over 80 flyovers planned for Indore, second only to Surat Footi Kothi Bridge Planned to be built in 18 months A Thirty Five Storey complex dedicated to startups to be built in the Business Hub Indore Pithampur will get a green field city project and 1000Cr to develop 200 Feet deep tunnel being built near Simrol, Bherughat , will reduce distance by 5 km Indore on track to become the ultimate Flyover City Tender to be issued for elevated track of Metro from Robot-Bengali Chauraha to Palasia