Preparing for a new path * This corridor will be different from the existing road.
NHAI will sign MoU for 4900 km roads of MP
415 km long corridor
National Highway Authority of India (NHAI) is going to build a ‘green field high speed corridor’ between Indore-Bhopal-Jabalpur. It will be different from the existing road and the route will be designed from a place where there has never been a road before. Commercial areas will also be developed around these two corridors. Bhopal to Indore corridor will be 160 km long. The cost will be Rs 9,716 crore.
Bhopal to Jabalpur corridor will be 255 km long. The proposed cost is 14,105 crores. NHAI is going to sign an MoU with the MP government at the Global Investors Summit to complete a total of 25 road projects along with these two big projects by 2047. The length of all these projects is 4900 km. 1 lakh 30 thousand 800 crores will be spent on this.
This special-
25 Road Projects.
Indore Ring Road Will be completed.
1.30 will be lakh crore rupees.
These projects in the first phase, which will be built new Project
Project km Cost
Lakhnadon-Raipur 200 9603
Kota-Etawah 394 9850
Agra-Gwalior 88 4613
Betul-Khandwa-Khargone-Julwania 233 4992
Ujjain-Jhalawar (four lane) 124 2232
(Western-Eastern Bypass) by 2047 141 6500
Jabalpur-Damnod 100 2500
Satna-Chitrakoot (four lane) 80 1440
Rewa-Sidhi (Four Lane) 60 1500
Sandalpur-Nasrullaganj (four lane) 43 1425
Gwalior Western Bypass (Four Lane) 29 1226
Sagar Bypass (Four Lane) 20 785
Ayodhya Nagar Bypass 16 1050
Orchha Bypass 14 336
This exercise was done after examining the traffic data
By signing the MoU, NHAI will get help in land acquisition, utility shifting and at the local level. NHAI wants to start its vision for the next 15 years right now. This exercise will move forward with the MoU. Existing routes have to be upgraded. NHAI has analyzed its traffic data. There are preparations to work on that basis.