4 bridges, 3 bypasses on Ring Road, 3 AB Roads and 1 bridge on Indore-Ujjain Road are taking shape, people will save up to 30 minutes in travel time.

One lane of Khajrana flyover on Bhaskar Audit Ring Road is 90% ready, 65% work of Bhanwarkuan flyover has been done.

Work on 11 flyovers is going on simultaneously in the city. All the flyovers will be ready in one and a half to two years. With their construction, the road to AB Road, Ring Road, Bypass as well as Indore-Ujjain Road will become easier. Maximum work of 4 flyovers is going on on the Ring Road. 3 flyover work is going on on AB Road and 3 flyover work is going on bypass. The double-decker bridge being built at Lavkush intersection will ease the journey between Indore-Ujjain.

  • 10 to 90 percent work has been completed – 10 to 90 percent work of various flyovers has been completed. All three bridges on the bypass (Rau, Ralamandal and MR-10 junction) are being built by NHAI. IDA is constructing Bhanwarkuan, Khajrana, Footi Kothi and Lavkush intersection flyovers. Whereas MPRDC is doing the work of Satyasai, Musakhedi, Dewas Naka and IT Park flyover.

Flyovers will speed up Indore’s move towards metropolitan city.

These 11 flyovers will give speed to Indore moving towards metropolitan city. The places where these are being built were all important parts of the Municipal Corporation’s City Mobility Plan. Construction of the bridge here will speed up the city’s traffic. people’s travel.

Time will be less. The flyover being built on the city’s central road AB Road i.e. the existing BRTS will solve the problem of traffic jams at intersections. The flyovers being built on the Ring Road will make the traffic signal free. The double decker bridge being built on Indore-Ujjain road will prove important in view of Simhastha.

  1. Khajrana (Ring Road)
  • 90% work of one lane has been done
  • 80% work of the second arm has been completed. Both arms are different.
  • 1 arm will start in June
  • The second arm will be ready by December
  1. IT Park (Ring Road)
  • 10% work done. Construction of this bridge started a month ago
  • Plan to complete work by September 2025. The construction of this bridge will also benefit the traffic of Indore-Khandwa road.
  1. Musakhedi (Ring Road)
  • 10% has been completed. one month

start making first

  • Plan to complete work by September 2025
  1. Footikothi (Ring Road)
  • 80% work has been completed
  • Will be ready by December this year

Rau Circle (Bypass)

  • 80% work done.

MR-10 Junction (Bypass)

    • 25% work has been completed
    • Work in 2 separate parts
    • An underpass and a flyover are being built here.
    • Will be ready in one and a half to two years. The junction will be jam free.

    Ralamandal (Bypass)

      • 40% work completed
      • Will start by January 2025

      Dewas Naka (AB Road)

        • 10% work done. Started construction a month ago
        • Plan to complete work by September 2025

        Satyasai (AB Road)

          • 10% work done. Started construction a month ago
          • Plan to complete work by September 2025

          Bhanwarkuan (AB Road)

            • 65% work has been completed
            • Will be ready by December this year

            Lavkush (Indore-Ujjain Road)

              • 70% work done
              • Will be built by the end of this year.

              Source- Dainik Bhaskar